Construction Begins At Woodstone

DSCN1006DSCN0994DSCN0997DSCN1011DSCN1012DSCN1016DSCN1023DSCN1015DSCN1027DSCN1035

 

 

Using a backhoe and a bulldozer, the crew clears the site of rocks, debris and trees for the house and the septic system. The crew levels the site, puts up wooden forms to serve as a template for the foundation, and digs the holes and trenches. Footings (structures where the house interfaces with the earth that supports it) are installed.

The hole is dug for the full basement, the footings are formed and poured, and the foundation walls are formed and poured. The area between them is leveled and fitted with utility runs (e.g. plumbing drains and electrical chases).

After the concrete is cured, the crew applies a waterproofing membrane to the foundation walls; installs drains, sewer and water taps and any plumbing that needs to go into the basement floor; and backfills excavated dirt into the hole around the foundation wall.

This next week will be exciting as the lumber is being delivered and the walls will start going up. The barn foundation is also being poured this week and the old barn form from Pennsylvania will arrive early next week.

2 thoughts on “Construction Begins At Woodstone

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s